CALIFORNIA MEN’S COLONY
1997 DIGESTER REPLACEMENT PROJECT

DESIGN & CONSTRUCTION SERVICES
COST: $1.0 MILLION - JUNE 1997
CONTRACTOR: STATE OF CA

Designed a $1.0 million 0.25-million-gallon anaerobic digester with boiler, sludge grinder, spiral heat exchanger (SHE) unit and pump mix systems.

Construction of the concrete anaerobic digester.


2505 30TH STREET SANTA MONICA, CA 90405
PHONE (310) 392-3137 FAX (310) 392-3124 CELL NO. (310) 864-2157