DESIGN & CONSTRUCTION SERVICES
COST: $1.10 MILLION October 1995 - August 1996
CONTRACTOR: GENTZ CONSTRUCTION
Construction of concrete
secondary sedimentation structural walls.
The project
included design and construction management with inspection of a secondary
sedimentation basin and other plant modifications. The contractor went bankrupt
half way through the project and the project was finished with the bonding
company and their representative. The project was finished within budget and
with no financial impact to the Owner.