1995 WWTF Treatment Plant Additions Clarifier Expansion Project

DESIGN & CONSTRUCTION SERVICES
COST: $1.10 MILLION October 1995 - August 1996
CONTRACTOR: GENTZ CONSTRUCTION

 

Construction of concrete secondary sedimentation structural walls.

The project included design and construction management with inspection of a secondary sedimentation basin and other plant modifications. The contractor went bankrupt half way through the project and the project was finished with the bonding company and their representative. The project was finished within budget and with no financial impact to the Owner.
     
  Sedimentation Basin Concrete Wall Form Placement.  

Sedimentation Basin Concrete Effluent Overflow Box.

  Sedimentation Basin Concrete Wall After Form Removal.
     
  Sedimentation Basin Concrete Wall Interior Form and Rebar Placement.   Sedimentation Basin Concrete Wall Exterior Form Placement.   Scum Pump Station Manhole

2505 30TH STREET SANTA MONICA, CA 90405
PHONE (310) 392-3137 FAX (310) 392-3124 CELL NO. (310) 864-2157
E-MAIL:
watsoncm@earthlink.net
©2000-2010 Watson Consulting Engineers Inc. All Rights Reserved.