Simi Valley
SV07-11 LA Avenue, Madera Road, Lysander Avenue Sewer Trunk Project |
 |
Simi Valley SV 07-11 Los Angeles Avenue, Madera Road, Lysander Avenue Sewer
Trunk Project$3.25 MILLION - JULY
2007 - MARCH 2009WCE
PROVIDED
PROJECT CONSTRUCTION SUPPORT AND INSPECTION SERVICES
CONTRACTOR: COLICH LLP, EUGENIO MATEO PROJECT MANAGER
|
Lysander Avenue - Dewatering
Well Construction

Click on photo to enlarge.
Dewatering and Construction Work Sequence:
- Set up traffic control.
- Notify Homeowners - public
outreach.
- Contact USA DigAlert,
identify buried utilities.
- Locate sewer laterals and identify
utilities.
- Drill dewatering wells.
- Setup dewatering field, silt tank
and sewer by-pass.
- Allow for de-watering of
site.
- Saw-cut asphalt street surface.
- Excavate sewer trench and install
new sewer main.
- Backfill and return street surface
to former condition.
|
 |
Lysander Avenue
DIG AND REPLACE EXISTING 8 INCH
VCP SEWER WITH NEW 10 INCH PVC SEWER
(TOP) LYSANDER AVENUE SEWER
REPLACEMENT EXCAVATE, TRENCH, PIPE REPLACEMENT AND BACKFILL (BOTTOM).
Excavated and open trenched 859
linear feet of 8 inch VCP with new 10 inch SDR 35 PVC Sewer Pipe.
|

Sewer Lateral Excavation |

Sewer Lateral Trench Shielding |

Connection of new PVC to Existing Clay with Coupling |

Slurry Backfill over Pipe in Trench |
 |
Madera Road
SLIPLINING OF EXISTING
27 INCH RCP SEWER WITH 24 INCH HOBAS® FRPMP.
Slip-lined 3,182 feet of 27-inch
RCP Sewer Pipe with 24 inch Hobas liner pipe. |

Field Installation of Hobas Pipe |

Field Installation of Hobas Pipe |
LINER PIPE
FABRICATOR: BY HOBAS® CLICK ON AN IMAGE TO
ENLARGE IT.
|

Field Closure of Hobas Pipe prior to Concrete Encasement. |
 Slurry backfill to Grade over Field
Closure. |
 |
Los Angeles Avenue
27 INCH CIPP, CURED IN PLACE PIPE
AND
SLIPLINING OF EXISTING
27 INCH RCP SEWER WITH 24 INCH HOBAS® FRPMP.
Slip-lined 3,182 feet of
27-inch RCP Sewer Pipe with 24 inch Hobas liner pipe.
LINER PIPE
FABRICATOR: BY HOBAS, CIPP - BY WESCO |

Sewer Bypass Pumping Setup for CIPP Installation. (Godwynn
By-Pass Pumping) |

Inserting CIPP Liner from Sub-Contractor (Wesco) Stationing Truck. |
|
|
|
|

Lowering Test Mandrel into access pit into opened sewer
pipe. |

Mandrel to check Joint Offsets prior to installing liner
pipe. |

Note Debris on Mandrel after Testing. Mandrel is not
intended for use as a cleaning device. |

Stockpile of Hobas Pipe. |

Pushing Head for Hobas® Installation. |

Excavated Pipe Jacking Pit. |