Castaic Lake Water Agency | |
Sand Canyon Pipeline Project$23.4 MILLION - JULY 2004 - OCT 2006PROJECT MANAGEMENT AND INSPECTION SERVICES CONTRACTOR: L.H. WOODS CONSTRUCTION, BOB KERTIS PROJECT SUPERINTENDENT SET No. 1 TUNNELING UNDER CAMP PLENTY ROAD AT SOLEDAD CANYON ROAD INTERSECTION. |
|
|
Sand Canyon Pipeline Project5.0 MILES CEMENT MORTAR LINED AND COATED 48" DIAMETER STEEL PIPEDUAL WELD INTERIOR AND EXTERIOR FABRICATOR: AMERON INTERNATIONAL, LEROY KUZEL SET No. 2 TUNNELING UNDER THE SANTA CLARA RIVER. |
Sand Canyon Pipeline ProjectSET No. 3 PIPELINE CONSTRUCTION ACROSS THE SANTA CLARA RIVER. |
|
2505 30TH STREET SANTA MONICA, CA 90405 PHONE (310) 392-3137 FAX (310) 392-3124 CELL NO. (310) 864-2157 E-MAIL: watsoncm@earthlink.net ©2000-2006 Watson Consulting Engineers Inc. All Rights Reserved. |