California State University Channel Islands East Campus Recycled Water Project

Purpose: To provide Title 22 Water Recycled water from a tertiary disinfected wastewater effluent to the University for irrigation and landscape needs. The use of the recycled water is approximately one fifth the cost of Class 1 water from the California aqueduct and /or groundwater pumped from the local community. A Joint effort between the Camrosa Water District and the California State University Channel Islands.

East Campus Recycled Water Project

$1 MILLION - JULY 2004

PROVIDED ENGINEERING REPORTS AND PROJECT DESIGN SERVICES

Powerpoint slide of the site plan.

Transmission pipeline site plan click to enlarge.

PROJECT COMPONENTS: EFFLUENT PUMPS, C905 PVC FORCEMAIN, CONTROL VALVES, DUCTILE IRON FITTINGS AND PIPE SECTION, ELECTRICAL COMPONENTS UTILITY VAULT BOXES, INSTRUMENTATION CONTROL AND EXTENSIVE STRUCTURAL REHABILITATION TO EXISTING CONCRETE RESERVOIR, CAST IRON PIPELINE AND INFRASTRUCTURE.

Click on an image to enlarge it.

  Pipeline approach to bridge. Pipeline supported by pipe hangers. Pipeline approach from bridge. Pipeline control valves in vault box.

2505 30TH STREET SANTA MONICA, CA 90405
PHONE: (310) 392-3137 FAX (310) 392-3124 CELL NO. (310) 864-2157